In 2005 Norfolk, NE voters approved a $9.345.000 school bond for remodeling and
additions to existing elementary buildings and the Middle School building.
Voters in addition approved an $11,425,000 school bond for remodeling and
additions to the existing Junior High and Senior High school buildings. The
total school bond issue was $20,770,000.
-
Bel Air Elementary -- NOW COMPLETED
Project includes parking and sidewalk expansion; Administrative, classroom,
and multipurpose room additions, miscellaneous interior remodel work and
addition of a fire sprinkler system for the entire building.
-
Senior High -- IN PROGRESS
Project includes four new additions and miscellaneous remodeling areas throughout the
existing Senior High School. The additions consist of a new Media and Administrative
Center and entrance, new entrance to the gymnasium with new concessions and restrooms,
weight/fitness center and science classroom wing. New fire sprinkler system for entire
building excluding the Carson Theater.
-
Junior High -- IN PROGRESS
Project includes construction of a 7481 sq ft Administrative and classroom addition,
mechanical and electrical upgrades, fire sprinkler system, and miscellaneous renovation
and interior finish work.