Just off Highway 275 in Norfolk, a brand-new Prime Stop is taking shape, and it’s almost ready to welcome the community.

This roughly 6,000SF convenience store and fueling station is in the final stretch of construction. Inside, things are really coming together. Casework is being installed in the retail area and most of the interior finishes are nearly complete! You can start to picture what it will look like when shelves are stocked and the doors open for business.

Outside, the crews are currently pouring the ten-inch paving that will support truck traffic, making sure the station can handle everything from daily commuters to long-haul drivers. The six-inch paving, designed for lighter vehicles, is coming soon, rounding out a well-planned layout that’s built to last.

Fuel canopies are also going up, bringing the look and function of the site full circle. The diesel canopy is already in place and the gas canopy will follow in the next couple of weeks. With each update, the vision of Prime Stop is becoming more and more real.

This new stop isn’t just about fuel it’s also about providing a clean, reliable, and convenient place for people on the go. Whether you’re filling up before work, grabbing a snack for the road, or making a quick stop during your travels, Prime Stop is being built with the community in mind.

Stay tuned, we’re just a few steps away from opening day, and we’re excited to see this project come to life for Norfolk and the surrounding community.

 
 